- Practice. Work. Civic
3.2.5_07
- Title of Project
Qingpu Plot-18 Cultural Facilities
- Program. Intervention
Church, Club House. New
- Responsibility
Site Project Director
- Principal
Juan C. Sancho + Sol Madridejos
- Team
CA-Group. Pedro P. Arroyo Alba, Zhiqiu Xia
- Consultant
Shanghai Municipal Engineering Design Institute (Group) Co. Ltd.
- Contractor
Shanghai Forte Land (Group) Co. Ltd.
- Client
S-MAO Sancho-Madridejos Architecture Office
- Type of Procurement
Commission
- Scope of Work
Project Management
- Location
- CN. Shanghai. Qingpu (31.14217, 121.11957)
- Date of Design
2004/10/30
- Date of Construction
2005/04-2006/04
- Duration
M 12
- Language of Documentation
English, Spanish, Chinese
- Site Area-Built Area
sqm 6.000-sqm 4.500
- Construction Cost
(undisclosed)
To be continued…