- Practice. Work. Infrastructure
3.2.1_15
- Title of Project
YP10B Nº 4-9, 1. Concrete+Wood Zigzag II
- Program. Intervention
Pedestrian-Road Bridges. New
- Responsibility
Author
- Principal
Pedro P. Arroyo Alba
- Team
CA-Group. Ning Li
- Consultant
Shanghai Xiandai Architecture Design (Group) Co. Ltd.
- Contractor
China Construction Engineering Fifth Division
- Client
Shanghai Jiading Newcity Development Co. Ltd.
- Type of Procurement
Commission
- Scope of Work
Design Development, Construction Drawings, Site Supervision
- Location
- CN. Shanghai. Jiading (31.35092, 121.26388)
- Date of Design
2009/06
- Date of Construction
2010/02-2011/10
- Duration
M 18
- Language of Documentation
English, Chinese
- Site Area-Built Area
sqm 6.912-sqm 3.072
- Construction Cost
EUR 1.202.500
To be continued…